Peter Espeut | He who feels it, knows it

Published:Friday | October 4, 2024 | 12:06 AM
This aerial photo shows Bull Bay, St Thomas, Police Station slated to be relocated as part of new roadway being developed under the Southern Coastal Highway Improvement Project.
This aerial photo shows Bull Bay, St Thomas, Police Station slated to be relocated as part of new roadway being developed under the Southern Coastal Highway Improvement Project.

I live about one mile down the road from Harbour View in St Andrew to Yallahs in St Thomas. In January 2017 the Government of Jamaica commenced construction of a four-lane highway from Harbour View to Yallahs designated as Part B II of the Southern Coastal Highway Improvement Project (SCHIP) implemented by the Ministry of Economic Growth and Job Creation, headed by Prime Minister Andrew Holness.

The government calls this a “flagship project”, by which I think they mean that they intend to make it a showpiece of what they are capable of, a demonstration of good and efficient project management.

I cannot determine when the project was initially projected to be completed, but a Press Release issued on February 24, 2021 by the Jamaica Special Economic Zone Authority of the Ministry of Industry, Investment and Commerce announced that “A sum of $17.4 billion has been allotted in the 2021/22 Estimates of Expenditure to continue implementation of the Southern Coastal Highway Improvement Project (SCHIP)”; and that “Following several extensions, the project, which began in January 2017, is slated to end in March 2022” (see https://www.jseza.com/17-4-billion-set-aside-for-southern-coastal-highwa...).

A revised deadline – after several extensions – of March 2022.

ANOTHER REVISED DEADLINE

Making his Sectoral Presentation in Parliament on May 31, 2023, then Minister without portfolio in the Ministry of Economic Growth and Job Creation, Clifford E. Warmington, declared that the component of the Southern Coastal Highway Improvement Project (SCHIP) from Harbour View to Yallahs was now 93 per cent complete, and that this section of the SCHIP would be complete by the end of August 2023.

It didn’t happen! August 2023 came and went. So did August 2024.

On December 14, 2023 the JIS issued a press release advising that all lanes along the Harbour View to Yallahs Bridge leg of the Southern Coastal Highway are now open for use: “Starting today, December 14, 2023, persons traversing this section of the corridor are able to access all four lanes as was committed under the programme of works currently being carried out”.

That announcement was premature and inaccurate. At the time sections of the highway in both directions were restricted to one lane. Even today.

Of course, the local government elections were imminent, and a good show had to be staged. Despite the road construction being incomplete, on February 6, Prime Minister Holness presided over an elaborate eight-person ribbon-cutting ceremony declaring that section of SCHIP officially open.

Local government elections were held on February 26.

NOT EVEN FIRST MILE COMPLETE

Eight months have now elapsed. This is now October and not even the first mile down the road from Harbour View to Yallahs is fully complete after seven-and-a-half years! Drivers have to dodge holes in the roadway, endure rough unpaved sections (recently dug up and filled in but not yet paved), and in some places, navigate between piles of soil in the roadway which restrict traffic to one lane only.

In the heavy rains last month a section of the roadway opposite Copacabana was inundated, such that cars were flooded. The construction has changed the runoff water flow, and the new drains are not able to handle the volume. As you read this, the area is again being dug up to modify the drains.

One expects temporary inconvenience during road construction. That roadway is well-travelled; it is estimated that 14,000 vehicles pass on that thoroughfare daily. Over the seven-plus years there have been horrendous delays and traffic pile-ups; not to mention the dust nuisance.

On July 10, 2023 construction activity resulted in broken water mains which caused a massive traffic jam for commuters passing through Seven Miles, Bull Bay. The problem caused by the broken mains and the backlash from the affected commuters prompted the direct intervention of the prime minister; the day after the incident, E.G Hunter, chief executive officer of the National Works Agency (NWA), was instructed by the prime minister to exert direct supervision of the project to ensure its timely completion.

Road construction is ongoing.

But there will also be permanent inconvenience. The median dividing the road is a waist-high wall, as if the intention was to build a toll road in an isolated area. The road passes through Bull Bay – a heavily populated area; only agile young people can easily climb over the wall to cross the road; it is impossible for the old and infirm to do so.

A church sister of mine who lives in Camrose – an older person who regularly takes the bus – said to me recently: “Look at what dem do to wi bus stop?” There is no gap in the wall by or near Camrose to accommodate pedestrians crossing the road to the green-painted bus stop. I guess the colour will remind them of the source of their inconvenience.

I have pointed out before in this column that were the recent elections general rather than local, the constituency of East Rural St Andrew in which Bull Bay and Camrose fall would flip to the opposition.

So much for the flagship project!

I understand from a recent announcement that the new completion date for the SCHIP Harbour View to Yallahs roadway is March 2025.

Let’s see!

Peter Espeut is a sociologist and development scientist. Send feedback to columns@gleanerjm.com